Workflow steps
6 of 12 complete
- Dec 21
1. Trash Out
TurnPro Services
- Dec 22
2. Demo
ABC Construction
- Dec 23
3. Plumbing
ABC Plumbing
- Dec 24
4. Electrical
XYZ Electric
- Dec 25
5. Cabinets
ABC Construction
- Dec 26
6. Countertops
ABC Construction
- Dec 28
7. Flooring
FloorCo Surfaces
- Dec 29
8. Paint
Lonestar Painting
- Dec 30
9. Appliances
ABC Construction
- Dec 31
10. QC
ABC Construction
- Jan 1
11. Punch
ABC Construction
- Jan 2
12. Complete
ABC Construction
Assignments & visibility
Assignees own the work · viewers can see the project
- Controller / GCIn Progress
Project Control
ABC Construction
- AssigneeComplete
Trash Out
TurnPro Services
- AssigneeComplete
Demo
ABC Construction
- AssigneeComplete
Plumbing
ABC Plumbing
- AssigneeComplete
Electrical
XYZ Electric
- AssigneeComplete
Cabinets
ABC Construction
- AssigneeComplete
Countertops
ABC Construction
- AssigneeScheduled
Flooring
FloorCo Surfaces
- AssigneeScheduled
Paint
Lonestar Painting
- AssigneeScheduled
Appliances
ABC Construction
Photos
Before, condition, inspection and completion
Kitchen — before
Before · Dec 20
Living room — before
Before · Dec 20
Flooring progress
Condition · Dec 24
Bath resurfacing
Inspection · Dec 26
Activity
- Dec 19
John Smith · Submitted project for approval
- Dec 20
John Smith · Approved & launched workflow
- Dec 22
ABC Construction · Step "Countertops" marked complete
Unit
- Floor plan
- A2
- Square feet
- 754 SF
- Beds / baths
- 1 / 1
- Unit type
- Renovation
- Floor
- 8
- Building
- 1
Project details
- Workflow type
- Partial Renovation
- Assignment model
- Model A — GC controls all
- GC / controller
- ABC Construction
- Submitted by
- John Smith
- Submitted
- Dec 19, 1969
- Start date
- Dec 21, 1969
- Target date
- Jan 3, 1970
Scope
Flooring replacement, paint, resurfaced bath.