Sunset Ridge: 305 - B3 (2x2) - Make Ready

PRJ-1011 · Standard Make Ready · Standard Make Ready v3

In ProgressAt Risk

Workflow steps

2 of 6 complete

  1. 1. Trash Out

    TurnPro Services

    Dec 29
  2. 2. Clean

    TurnPro Services

    Dec 30
  3. 3. Paint Touch Up

    Lonestar Painting

    Dec 31
  4. 4. Carpet / Flooring

    FloorCo Surfaces

    Jan 1
  5. 5. Punch

    Onsite Team

    Jan 1
  6. 6. Ready Inspection

    Onsite Team

    Jan 2

Assignments & visibility

Assignees own the work · viewers can see the project

  • Trash Out

    TurnPro Services

    AssigneeComplete
  • Clean

    TurnPro Services

    AssigneeComplete
  • Paint Touch Up

    Lonestar Painting

    AssigneeScheduled
  • Carpet / Flooring

    FloorCo Surfaces

    AssigneeScheduled
Sarah Delgado · AssigneeMarcus Webb · ViewerTina Alvarez · Assignee

Photos

Before, condition, inspection and completion

Kitchen — before

Before · Dec 28

Living room — before

Before · Dec 28

Flooring progress

Condition · Dec 31

Bath resurfacing

Inspection · Dec 31

Activity

  • Dec 27

    Sarah Delgado · Submitted project for approval

  • Dec 28

    John Smith · Approved & launched workflow

  • Dec 30

    Onsite Team · Step "Clean" marked complete

Unit

Sunset Ridge · Unit 305B3 · 1,050 SF · 2 Bed / 2 Bath · Make Ready
Floor plan
B3
Square feet
1,050 SF
Beds / baths
2 / 2
Unit type
Make Ready
Floor
3
Building
4

Project details

Workflow type
Standard Make Ready
Assignment model
Model C — vendor direct
GC / controller
Unassigned
Submitted by
Sarah Delgado
Submitted
Dec 27, 1969
Start date
Dec 29, 1969
Target date
Jan 3, 1970

Scope

Turn ahead of new lease start.

Details incomplete

Can be completed later — not blocking

  • Vendor assignment: Flooring