Riverside: 306 - B2 (2x2) - Classic

PRJ-1015 · Full Renovation · Full Renovation v4

CompleteOn Track

Workflow steps

12 of 12 complete

  1. 1. Trash Out

    TurnPro Services

    Nov 16
  2. 2. Demo

    ABC Construction

    Nov 19
  3. 3. Plumbing

    ABC Plumbing

    Nov 22
  4. 4. Electrical

    XYZ Electric

    Nov 25
  5. 5. Cabinets

    ABC Construction

    Nov 27
  6. 6. Countertops

    ABC Construction

    Nov 30
  7. 7. Flooring

    FloorCo Surfaces

    Dec 3
  8. 8. Paint

    Lonestar Painting

    Dec 6
  9. 9. Appliances

    ABC Construction

    Dec 9
  10. 10. QC

    ABC Construction

    Dec 12
  11. 11. Punch

    ABC Construction

    Dec 14
  12. 12. Complete

    ABC Construction

    Dec 17

Assignments & visibility

Assignees own the work · viewers can see the project

  • Project Control

    ABC Construction

    Controller / GCComplete
  • Trash Out

    TurnPro Services

    AssigneeComplete
  • Demo

    ABC Construction

    AssigneeComplete
  • Plumbing

    ABC Plumbing

    AssigneeComplete
  • Electrical

    XYZ Electric

    AssigneeComplete
  • Cabinets

    ABC Construction

    AssigneeComplete
  • Countertops

    ABC Construction

    AssigneeComplete
  • Flooring

    FloorCo Surfaces

    AssigneeComplete
  • Paint

    Lonestar Painting

    AssigneeComplete
  • Appliances

    ABC Construction

    AssigneeComplete
Sarah Delgado · AssigneeMarcus Webb · ViewerTina Alvarez · Assignee

Photos

Before, condition, inspection and completion

Kitchen — before

Before · Nov 15

Living room — before

Before · Nov 15

Flooring progress

Condition · Nov 19

Bath resurfacing

Inspection · Nov 21

Activity

  • Nov 14

    Sarah Delgado · Submitted project for approval

  • Nov 15

    John Smith · Approved & launched workflow

  • Nov 17

    ABC Construction · Step "Punch" marked complete

Unit

Riverside · Unit 306B2 · 962 SF · 2 Bed / 2 Bath · Classic
Floor plan
B2
Square feet
962 SF
Beds / baths
2 / 2
Unit type
Classic
Floor
3
Building
2

Project details

Workflow type
Full Renovation
Assignment model
Model B — GC + vendor steps
GC / controller
ABC Construction
Submitted by
Sarah Delgado
Submitted
Nov 14, 1969
Start date
Nov 16, 1969
Target date
Dec 20, 1969

Scope

Full renovation delivered on schedule.