Riverside: 1102 - B2 (2x2) - R-Unit

PRJ-1016 · Full Renovation · Full Renovation v4

In ProgressAt Risk

Workflow steps

2 of 12 complete

  1. 1. Trash Out

    TurnPro Services

    Dec 27
  2. 2. Demo

    ABC Construction

    Dec 28
  3. 3. Plumbing

    ABC Plumbing

    Dec 29
  4. 4. Electrical

    XYZ Electric

    Dec 30
  5. 5. Cabinets

    ABC Construction

    Dec 31
  6. 6. Countertops

    ABC Construction

    Jan 1
  7. 7. Flooring

    FloorCo Surfaces

    Jan 2
  8. 8. Paint

    Lonestar Painting

    Jan 2
  9. 9. Appliances

    ABC Construction

    Jan 3
  10. 10. QC

    ABC Construction

    Jan 4
  11. 11. Punch

    ABC Construction

    Jan 5
  12. 12. Complete

    ABC Construction

    Jan 6

Assignments & visibility

Assignees own the work · viewers can see the project

  • Project Control

    ABC Construction

    Controller / GCIn Progress
  • Trash Out

    TurnPro Services

    AssigneeComplete
  • Demo

    ABC Construction

    AssigneeComplete
  • Plumbing

    ABC Plumbing

    AssigneeScheduled
  • Electrical

    XYZ Electric

    AssigneeScheduled
  • Cabinets

    ABC Construction

    AssigneeScheduled
  • Countertops

    ABC Construction

    AssigneeScheduled
  • Flooring

    FloorCo Surfaces

    AssigneeScheduled
  • Paint

    Lonestar Painting

    AssigneeScheduled
  • Appliances

    ABC Construction

    AssigneeScheduled
Sarah Delgado · AssigneeMarcus Webb · ViewerTina Alvarez · Assignee

Photos

Before, condition, inspection and completion

Kitchen — before

Before · Dec 26

Living room — before

Before · Dec 26

Flooring progress

Condition · Dec 30

Bath resurfacing

Inspection · Dec 31

Activity

  • Dec 25

    Sarah Delgado · Submitted project for approval

  • Dec 26

    John Smith · Approved & launched workflow

  • Dec 28

    ABC Construction · Step "Demo" marked complete

Unit

Riverside · Unit 1102B2 · 962 SF · 2 Bed / 2 Bath · R-Unit
Floor plan
B2
Square feet
962 SF
Beds / baths
2 / 2
Unit type
R-Unit
Floor
11
Building
5

Project details

Workflow type
Full Renovation
Assignment model
Model B — GC + vendor steps
GC / controller
ABC Construction
Submitted by
Sarah Delgado
Submitted
Dec 25, 1969
Start date
Dec 27, 1969
Target date
Jan 7, 1970

Scope

Full renovation, premium finish package.

Details incomplete

Can be completed later — not blocking

  • Vendor assignment: Cabinets