Riverside: 415 - A2 (1x1) - Make Ready

PRJ-1017 · Standard Make Ready · Standard Make Ready v3

In ProgressOverdue

Workflow steps

3 of 6 complete

  1. 1. Trash Out

    TurnPro Services

    Dec 24
  2. 2. Clean

    TurnPro Services

    Dec 25
  3. 3. Paint Touch Up

    Lonestar Painting

    Dec 26
  4. 4. Carpet / Flooring

    FloorCo Surfaces

    Dec 28
  5. 5. Punch

    Onsite Team

    Dec 29
  6. 6. Ready Inspection

    Onsite Team

    Dec 30

Assignments & visibility

Assignees own the work · viewers can see the project

  • Trash Out

    TurnPro Services

    AssigneeComplete
  • Clean

    TurnPro Services

    AssigneeComplete
  • Paint Touch Up

    Lonestar Painting

    AssigneeComplete
  • Carpet / Flooring

    FloorCo Surfaces

    AssigneeScheduled
Sarah Delgado · AssigneeMarcus Webb · ViewerTina Alvarez · Assignee

Photos

Before, condition, inspection and completion

Kitchen — before

Before · Dec 23

Living room — before

Before · Dec 23

Flooring progress

Condition · Dec 27

Bath resurfacing

Inspection · Dec 29

Activity

  • Dec 22

    Sarah Delgado · Submitted project for approval

  • Dec 23

    John Smith · Approved & launched workflow

  • Dec 25

    Onsite Team · Step "Paint Touch Up" marked complete

Unit

Riverside · Unit 415A2 · 754 SF · 1 Bed / 1 Bath · Make Ready
Floor plan
A2
Square feet
754 SF
Beds / baths
1 / 1
Unit type
Make Ready
Floor
4
Building
5

Project details

Workflow type
Standard Make Ready
Assignment model
Model C — vendor direct
GC / controller
Unassigned
Submitted by
Sarah Delgado
Submitted
Dec 22, 1969
Start date
Dec 24, 1969
Target date
Dec 31, 1969

Scope

Turn delayed by carpet backorder.

Details incomplete

Can be completed later — not blocking

  • Vendor assignment: Paint