Workflow steps
12 of 12 complete
- Nov 2
1. Trash Out
TurnPro Services
- Nov 5
2. Demo
ABC Construction
- Nov 7
3. Plumbing
ABC Plumbing
- Nov 10
4. Electrical
XYZ Electric
- Nov 12
5. Cabinets
ABC Construction
- Nov 15
6. Countertops
ABC Construction
- Nov 17
7. Flooring
FloorCo Surfaces
- Nov 20
8. Paint
Lonestar Painting
- Nov 22
9. Appliances
ABC Construction
- Nov 25
10. QC
ABC Construction
- Nov 27
11. Punch
ABC Construction
- Nov 30
12. Complete
ABC Construction
Assignments & visibility
Assignees own the work · viewers can see the project
- Controller / GCComplete
Project Control
ABC Construction
- AssigneeComplete
Trash Out
TurnPro Services
- AssigneeComplete
Demo
ABC Construction
- AssigneeComplete
Plumbing
ABC Plumbing
- AssigneeComplete
Electrical
XYZ Electric
- AssigneeComplete
Cabinets
ABC Construction
- AssigneeComplete
Countertops
ABC Construction
- AssigneeComplete
Flooring
FloorCo Surfaces
- AssigneeComplete
Paint
Lonestar Painting
- AssigneeComplete
Appliances
ABC Construction
Photos
Before, condition, inspection and completion
Kitchen — before
Before · Nov 1
Living room — before
Before · Nov 1
Flooring progress
Condition · Nov 5
Bath resurfacing
Inspection · Nov 7
Activity
- Oct 31
Sarah Delgado · Submitted project for approval
- Nov 1
John Smith · Approved & launched workflow
- Nov 3
ABC Construction · Step "Punch" marked complete
Unit
- Floor plan
- A1
- Square feet
- 685 SF
- Beds / baths
- 1 / 1
- Unit type
- R-Unit
- Floor
- 5
- Building
- 5
Project details
- Workflow type
- Full Renovation
- Assignment model
- Model B — GC + vendor steps
- GC / controller
- ABC Construction
- Submitted by
- Sarah Delgado
- Submitted
- Oct 31, 1969
- Start date
- Nov 2, 1969
- Target date
- Dec 2, 1969
Scope
Full renovation delivered.