Workflow steps
12 of 12 complete
- Nov 7
1. Trash Out
TurnPro Services
- Nov 9
2. Demo
ABC Construction
- Nov 12
3. Plumbing
ABC Plumbing
- Nov 14
4. Electrical
XYZ Electric
- Nov 16
5. Cabinets
ABC Construction
- Nov 18
6. Countertops
ABC Construction
- Nov 21
7. Flooring
FloorCo Surfaces
- Nov 23
8. Paint
Lonestar Painting
- Nov 25
9. Appliances
ABC Construction
- Nov 27
10. QC
ABC Construction
- Nov 30
11. Punch
ABC Construction
- Dec 2
12. Complete
ABC Construction
Assignments & visibility
Assignees own the work · viewers can see the project
- Controller / GCComplete
Project Control
ABC Construction
- AssigneeComplete
Trash Out
TurnPro Services
- AssigneeComplete
Demo
ABC Construction
- AssigneeComplete
Plumbing
ABC Plumbing
- AssigneeComplete
Electrical
XYZ Electric
- AssigneeComplete
Cabinets
ABC Construction
- AssigneeComplete
Countertops
ABC Construction
- AssigneeComplete
Flooring
FloorCo Surfaces
- AssigneeComplete
Paint
Lonestar Painting
- AssigneeComplete
Appliances
ABC Construction
Photos
Before, condition, inspection and completion
Kitchen — before
Before · Nov 6
Living room — before
Before · Nov 6
Flooring progress
Condition · Nov 10
Bath resurfacing
Inspection · Nov 12
Activity
- Nov 5
John Smith · Submitted project for approval
- Nov 6
John Smith · Approved & launched workflow
- Nov 8
ABC Construction · Step "Punch" marked complete
Unit
- Floor plan
- A2
- Square feet
- 754 SF
- Beds / baths
- 1 / 1
- Unit type
- R-Unit
- Floor
- 2
- Building
- 7
Project details
- Workflow type
- Partial Renovation
- Assignment model
- Model A — GC controls all
- GC / controller
- ABC Construction
- Submitted by
- John Smith
- Submitted
- Nov 5, 1969
- Start date
- Nov 7, 1969
- Target date
- Dec 4, 1969
Scope
Partial renovation delivered.