Parkview: 444 - B2 (2x2) - Make Ready

PRJ-1026 · Standard Make Ready · Standard Make Ready v3

CompleteOn Track

Workflow steps

6 of 6 complete

  1. 1. Trash Out

    TurnPro Services

    Dec 2
  2. 2. Clean

    TurnPro Services

    Dec 4
  3. 3. Paint Touch Up

    Lonestar Painting

    Dec 5
  4. 4. Carpet / Flooring

    FloorCo Surfaces

    Dec 7
  5. 5. Punch

    Onsite Team

    Dec 8
  6. 6. Ready Inspection

    Onsite Team

    Dec 10

Assignments & visibility

Assignees own the work · viewers can see the project

  • Trash Out

    TurnPro Services

    AssigneeComplete
  • Clean

    TurnPro Services

    AssigneeComplete
  • Paint Touch Up

    Lonestar Painting

    AssigneeComplete
  • Carpet / Flooring

    FloorCo Surfaces

    AssigneeComplete
Sarah Delgado · AssigneeMarcus Webb · ViewerTina Alvarez · Assignee

Photos

Before, condition, inspection and completion

Kitchen — before

Before · Dec 1

Living room — before

Before · Dec 1

Flooring progress

Condition · Dec 5

Bath resurfacing

Inspection · Dec 7

Activity

  • Nov 30

    Sarah Delgado · Submitted project for approval

  • Dec 1

    John Smith · Approved & launched workflow

  • Dec 3

    Onsite Team · Step "Punch" marked complete

Unit

Parkview · Unit 444B2 · 962 SF · 2 Bed / 2 Bath · Make Ready
Floor plan
B2
Square feet
962 SF
Beds / baths
2 / 2
Unit type
Make Ready
Floor
4
Building
7

Project details

Workflow type
Standard Make Ready
Assignment model
Model C — vendor direct
GC / controller
Unassigned
Submitted by
Sarah Delgado
Submitted
Nov 30, 1969
Start date
Dec 2, 1969
Target date
Dec 11, 1969

Scope

Turn completed.