Workflow steps
4 of 12 complete
- Dec 25
1. Trash Out
TurnPro Services
- Dec 26
2. Demo
ABC Construction
- Dec 27
3. Plumbing
ABC Plumbing
- Dec 28
4. Electrical
XYZ Electric
- Dec 28
5. Cabinets
ABC Construction
- Dec 29
6. Countertops
ABC Construction
- Dec 30
7. Flooring
FloorCo Surfaces
- Dec 31
8. Paint
Lonestar Painting
- Jan 1
9. Appliances
ABC Construction
- Jan 2
10. QC
ABC Construction
- Jan 2
11. Punch
ABC Construction
- Jan 3
12. Complete
ABC Construction
Assignments & visibility
Assignees own the work · viewers can see the project
- Controller / GCIn Progress
Project Control
ABC Construction
- AssigneeComplete
Trash Out
TurnPro Services
- AssigneeComplete
Demo
ABC Construction
- AssigneeComplete
Plumbing
ABC Plumbing
- AssigneeComplete
Electrical
XYZ Electric
- AssigneeScheduled
Cabinets
ABC Construction
- AssigneeScheduled
Countertops
ABC Construction
- AssigneeScheduled
Flooring
FloorCo Surfaces
- AssigneeScheduled
Paint
Lonestar Painting
- AssigneeScheduled
Appliances
ABC Construction
Photos
Before, condition, inspection and completion
Kitchen — before
Before · Dec 24
Living room — before
Before · Dec 24
Flooring progress
Condition · Dec 28
Bath resurfacing
Inspection · Dec 30
Activity
- Dec 23
John Smith · Submitted project for approval
- Dec 24
John Smith · Approved & launched workflow
- Dec 26
ABC Construction · Step "Electrical" marked complete
Unit
- Floor plan
- B2
- Square feet
- 962 SF
- Beds / baths
- 2 / 2
- Unit type
- R-Unit
- Floor
- 4
- Building
- 7
Project details
- Workflow type
- Full Renovation
- Assignment model
- Model B — GC + vendor steps
- GC / controller
- ABC Construction
- Submitted by
- John Smith
- Submitted
- Dec 23, 1969
- Start date
- Dec 25, 1969
- Target date
- Jan 4, 1970
Scope
Full renovation with quartz counters.
Details incomplete
Can be completed later — not blocking
- Vendor assignment: Countertops