Sunset Ridge: 220 - A2 (1x1) - R-Unit

PRJ-1030 · Full Renovation · Full Renovation v4

CompleteOn Track

Workflow steps

12 of 12 complete

  1. 1. Trash Out

    TurnPro Services

    Nov 14
  2. 2. Demo

    ABC Construction

    Nov 16
  3. 3. Plumbing

    ABC Plumbing

    Nov 18
  4. 4. Electrical

    XYZ Electric

    Nov 20
  5. 5. Cabinets

    ABC Construction

    Nov 22
  6. 6. Countertops

    ABC Construction

    Nov 24
  7. 7. Flooring

    FloorCo Surfaces

    Nov 26
  8. 8. Paint

    Lonestar Painting

    Nov 28
  9. 9. Appliances

    ABC Construction

    Nov 30
  10. 10. QC

    ABC Construction

    Dec 2
  11. 11. Punch

    ABC Construction

    Dec 4
  12. 12. Complete

    ABC Construction

    Dec 6

Assignments & visibility

Assignees own the work · viewers can see the project

  • Project Control

    ABC Construction

    Controller / GCComplete
  • Trash Out

    TurnPro Services

    AssigneeComplete
  • Demo

    ABC Construction

    AssigneeComplete
  • Plumbing

    ABC Plumbing

    AssigneeComplete
  • Electrical

    XYZ Electric

    AssigneeComplete
  • Cabinets

    ABC Construction

    AssigneeComplete
  • Countertops

    ABC Construction

    AssigneeComplete
  • Flooring

    FloorCo Surfaces

    AssigneeComplete
  • Paint

    Lonestar Painting

    AssigneeComplete
  • Appliances

    ABC Construction

    AssigneeComplete
Sarah Delgado · AssigneeMarcus Webb · ViewerTina Alvarez · Assignee

Photos

Before, condition, inspection and completion

Kitchen — before

Before · Nov 13

Living room — before

Before · Nov 13

Flooring progress

Condition · Nov 17

Bath resurfacing

Inspection · Nov 19

Activity

  • Nov 12

    John Smith · Submitted project for approval

  • Nov 13

    John Smith · Approved & launched workflow

  • Nov 15

    ABC Construction · Step "Punch" marked complete

Unit

Sunset Ridge · Unit 220A2 · 754 SF · 1 Bed / 1 Bath · R-Unit
Floor plan
A2
Square feet
754 SF
Beds / baths
1 / 1
Unit type
R-Unit
Floor
2
Building
8

Project details

Workflow type
Full Renovation
Assignment model
Model B — GC + vendor steps
GC / controller
ABC Construction
Submitted by
John Smith
Submitted
Nov 12, 1969
Start date
Nov 14, 1969
Target date
Dec 8, 1969

Scope

Full renovation delivered.