Oak Hollow: 340 - B3 (2x2) - Renovation

PRJ-1031 · Simple Renovation · Simple Renovation v1

In ProgressOn Track

Workflow steps

4 of 12 complete

  1. 1. Trash Out

    TurnPro Services

    Dec 26
  2. 2. Demo

    ABC Construction

    Dec 27
  3. 3. Plumbing

    ABC Plumbing

    Dec 28
  4. 4. Electrical

    XYZ Electric

    Dec 30
  5. 5. Cabinets

    ABC Construction

    Dec 31
  6. 6. Countertops

    ABC Construction

    Jan 1
  7. 7. Flooring

    FloorCo Surfaces

    Jan 2
  8. 8. Paint

    Lonestar Painting

    Jan 3
  9. 9. Appliances

    ABC Construction

    Jan 4
  10. 10. QC

    ABC Construction

    Jan 6
  11. 11. Punch

    ABC Construction

    Jan 7
  12. 12. Complete

    ABC Construction

    Jan 8

Assignments & visibility

Assignees own the work · viewers can see the project

  • Project Control

    ABC Construction

    Controller / GCIn Progress
  • Trash Out

    TurnPro Services

    AssigneeComplete
  • Demo

    ABC Construction

    AssigneeComplete
  • Plumbing

    ABC Plumbing

    AssigneeComplete
  • Electrical

    XYZ Electric

    AssigneeComplete
  • Cabinets

    ABC Construction

    AssigneeScheduled
  • Countertops

    ABC Construction

    AssigneeScheduled
  • Flooring

    FloorCo Surfaces

    AssigneeScheduled
  • Paint

    Lonestar Painting

    AssigneeScheduled
  • Appliances

    ABC Construction

    AssigneeScheduled
Sarah Delgado · AssigneeMarcus Webb · ViewerTina Alvarez · Assignee

Photos

Before, condition, inspection and completion

Kitchen — before

Before · Dec 25

Living room — before

Before · Dec 25

Flooring progress

Condition · Dec 29

Bath resurfacing

Inspection · Dec 31

Activity

  • Dec 24

    Priya Nair · Submitted project for approval

  • Dec 25

    John Smith · Approved & launched workflow

  • Dec 27

    ABC Construction · Step "Electrical" marked complete

Unit

Oak Hollow · Unit 340B3 · 1,050 SF · 2 Bed / 2 Bath · Renovation
Floor plan
B3
Square feet
1,050 SF
Beds / baths
2 / 2
Unit type
Renovation
Floor
3
Building
8

Project details

Workflow type
Simple Renovation
Assignment model
Model A — GC controls all
GC / controller
ABC Construction
Submitted by
Priya Nair
Submitted
Dec 24, 1969
Start date
Dec 26, 1969
Target date
Jan 9, 1970

Scope

Flooring, paint, fixtures.